| 1663168 | Apr 11, 2023 | BOILER INOPERABLE AT TIME OF INSPECTION CORRECT VIOLATION AND SUBMIT THE CERTIFICATE OF CORRECTION | Feb 5, 2024 | Admitted the violation | — |
| 1663164 | Apr 11, 2023 | BOILER INOPERABLE AT TIME OF INSPECTION;CORRECT VIOLATION AND SUBMIT THE CERTIFICATE OF CORRECTION | Feb 5, 2024 | Admitted the violation | — |
| 039083406J | Apr 11, 2023 | FAIL MAINTAIN BLDG IN COMPLIANT MANNER: SERVICE EQUIPMENT - BOILER | Feb 5, 2024 | Admitted the violation | — |
| 039083407L | Apr 11, 2023 | FAIL MAINTAIN BLDG IN COMPLIANT MANNER: SERVICE EQUIPMENT - BOILER | Feb 5, 2024 | Admitted the violation | — |
| 1448236 | Sep 16, 2021 | FAILURE TO MAINTAIN EXTERIOR BLDG FACADE & MAINTAINANCES.NOTE:AT THE TIME OF INSPECTION OBSERVED AT EXP.#4,NORTH ELEVATION,1 MISSING METAL PANELS AT 11TH FL,& 17TH FL,PANELS POSSIBLY LOOSE.REMEDY:MAINTAIN EXTE | Jan 26, 2022 | Admitted the violation | — |
| 035588951N | Sep 16, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Jan 26, 2022 | Admitted the violation | — |
| 1577459 | Aug 21, 2021 | FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES. NOTE:OBSERVED ON EXPOSURE 4,NORTH ELEVATION 1 MISSING METAL PANEL SECTION AND 2 ADDITIONAL MISALIGNED PANELS POSSIBLY LOOSE. REMEDY:MAINTAIN EXTER | Jan 12, 2022 | POP/IN-VIO | — |
| 035588707L | Aug 21, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Jan 12, 2022 | POP IN-VIOL | — |
| 035588805P | Aug 6, 2021 | UNLAWFUL ACTS.FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER | Dec 29, 2021 | POP IN-VIOL | — |
| 1534457 | Aug 6, 2021 | FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES.NOTE:OBSERVED AT EXPOSURE#4(NORTH)2 SLANTED/DISLODGED ALUMINUM PANELS ON 11THFLOOR AND 17TH FLOOR.REMEDY:MAINTAIN EXTERIOR BUILDING FACADE AND APPU | Dec 15, 2021 | POP/IN-VIO | — |
| 035578098X | Aug 6, 2021 | FAILURE PROVIDE SIDEWALK SHED WHERE REQUIRED | Dec 15, 2021 | POP IN-VIOL | — |
| 035578097Y | Aug 6, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Dec 15, 2021 | POP IN-VIOL | — |
| 295458 | Aug 6, 2021 | UNLAWFUL ACTS. FAILURE TO COMPLY W/ COMMISSIONERS ORDER. NOTE:DOB#061821FA0201DS REQUIRED THE OWNER TO PROVIDE A PE/RA REPORT TO THE FACADE UNIT DUE TO SLANTED/DISLODGED ALUMINUM PANELS AT 11TH AND 17TH FL OF E | Dec 29, 2021 | POP/IN-VIO | — |
| 1544599 | Aug 6, 2021 | FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED DUE TO 2 SLANTED/DISLODGED ALUMINUM PANELS AT 11TH FLOOR AND 17TH FLOOR,AT EXPOSURE#4(NORTH)REMEDY:PROVIDE SIDEWALK SHED. | Dec 15, 2021 | POP/IN-VIO | — |
| 1544408 | Jul 10, 2021 | FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED. NOTE:ECB#35559758Z AND ECB#35577715H REQUIRED THE OWNER TO PROVIDE SAFETY MEASURES(SWS) AT EXPOSURE#4,NORTH ELEVATION DUE TO SLANTED/DISLODGED ALUMINUM PANELS. A | Nov 17, 2021 | POP/IN-VIO | — |
| 1544459 | Jul 10, 2021 | FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE/WALLS AND APPURTENANCES. NOTE:AT THE TIME OF INSPECTION OBSERVED AT EXPOSURE 4,NORTH ELEVATION,2-SLANTED/DISLODGED ALUMINUM PANELS ON 11TH FL,AND 17TH FL. THESE ARE | Nov 17, 2021 | POP/IN-VIO | — |
| 035578027Z | Jul 10, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Nov 17, 2021 | POP IN-VIOL | — |
| 035578026R | Jul 10, 2021 | FAILURE PROVIDE SIDEWALK SHED WHERE REQUIRED | Nov 17, 2021 | POP IN-VIOL | — |
| 221175 | Jun 25, 2021 | UNLAWFUL ACTS FAILURE TO COMPLY WITH COMMISSIONERS ORDER NOTE :ECB #35559758Z ,35577712M , 35577715H AND DOB #Q51421CLLFA01MB REQUIRED THE OWNER TO PROVIDE SAFETY MEASURES AT EXPOSURE #4 (NORTH) DUE TO SLANTED | Nov 3, 2021 | Found in violation | — |
| 035577840R | Jun 25, 2021 | UNLAWFUL ACTS.FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER | Nov 3, 2021 | Found in violation | — |
| 035577715H | Jun 2, 2021 | FAILURE PROVIDE SIDEWALK SHED WHERE REQUIRED | Dec 8, 2021 | POP IN-VIOL | — |
| 1598291 | Jun 2, 2021 | FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED ECB#35559758Z REQUIRE THE OWNER TO PROVIDE SAFETY MEASURES(SIDEWALK SHED)AT EXP#4(NORTH)DUE TO SLANTED/DISLODGED ALUMINUM PANELS. AS OF 6/2/2021 NO SUCH SAFETY | Dec 8, 2021 | POP/IN-VIO | — |
| 220901 | Jun 2, 2021 | UNLAWFUL ACTS. FAILURE TO COMPLY W/COMM'S ORDER. ECB#35559758Z ISSUED ON 5/14/2021 REQUIRED THE OWNER TO PROVIDE SAFETY MEASURES. AS OF 6/2/2021 NO SAFETY MEASURES ARE IN PLACE. REMEDY: COMPLY W/COMM'S ORDER. | Dec 8, 2021 | POP/IN-VIO | — |
| 035577714X | Jun 2, 2021 | UNLAWFUL ACTS.FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER | Dec 8, 2021 | POP IN-VIOL | — |
| 1417684 | Jun 2, 2021 | FAILURE TO MAINTAIN EXTERIOR BLDG FACADE & APPURTENANCES. NOTE: OBSERVED AT EXP#4(NORTH),2 SLANTED/DISLODGED ALUMINUM PANELS ON 11TH & 17TH FLOORS. THESE ARE SAME CONDITIONS STATED IN PREVIOUS ECB#35559758Z. | Dec 8, 2021 | POP/IN-VIO | — |
| 035577712M | Jun 2, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Dec 8, 2021 | POP IN-VIOL | — |
| 035559758Z | May 14, 2021 | FAILURE TO MAINTAIN BUILDING WALL S OR APPURTENANCES | Nov 3, 2021 | Found in violation | — |
| 1481796 | May 14, 2021 | FAILURE TO MAINTAIN EXTERIOR BLDG FACADE OR APPURTENANCES.NOTE:ATOI OBSERVED 2 SLANTED-DISLODGED ALUMINUM PANELS ON 11&17FLS@EXP4N ELEVATION.ALSO OBSERVED 2PCS OF ALUMINUM PANELS HAVE BEEN REMOVED@5FL OF SAME E | Nov 3, 2021 | Found in violation | — |
| 1524667 | Mar 22, 2021 | FAILURE TO MAINTAIN BUILDING WALL OR APPURTENANCE. UPON INSPECTION, OBSERVED THREE LOOSE MEATAL PANELS AT THE EXPO#4, UNDER 5TH FLOOR GLASS WALL, WHICH IT MAY CAUSE A POTENTIAL HAZARD FOR PEDESTRIANS ON SIDEWAL | Apr 16, 2021 | POP/IN-VIO | — |
| 039038054M | Mar 22, 2021 | FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER | Apr 16, 2021 | POP IN-VIOL | — |
| 1355091 | Jan 10, 2019 | AT THE TIME OF MY INSPECTION CRANE USER EJM CONSULTING THE USER OF CRANE CD#4998 CN #619/18 AT 24 AKA 50 BRIDGE PARK DR BROOKLYN FAILED TO NOTIFY THE DEPARMTNET AS REQUIRED BY 3319-01(C)(S) OF THE CRANES DEPART | Jun 3, 2019 | Found in violation | — |
| 035360709Y | Jan 10, 2019 | EQUIP. USER FAILED TO PROPERLY NOTIFY THE DEPARTMENT | Jun 3, 2019 | Found in violation | — |
| 1347922 | Aug 27, 2018 | BC3301.2/HOLES/PENETRATION.AT TIME OF INSPECTION OF NB UP TO 30/ROOF LEVEL OBSERVED PENETRATIONS OF MORE THAN 3'(THREE INNCHES)IN DIAMETER AND ALSO PENETRATIONS OF MORE THAN 2'(TWO INCHES)X 4'(4 INCHES)OR LARGE | Nov 19, 2018 | Found in violation | — |
| 035345030M | Aug 27, 2018 | MISCELLANEOUS VIOLATIONS | Nov 19, 2018 | Found in violation | — |
| 1300941 | May 12, 2018 | SEC. 3303.4.5.2 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS-STORAGE NEAR UNENCLOSED PERIMETERS. NOTE: AT THE TIME OF MY INSPECTION OF A 30 STY BLDG AT 28TH FL LEVEL CONSTRUCTION WORK IN | Jul 17, 2018 | Found in violation | — |
| 1312846 | May 12, 2018 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS & OR APPROVEDAMENDMENTS. NOTE: AT THE TIME OF MY INSPECTION OF A 30 STY BLDG AT 28 FLOOR LEVEL,CONSTRUCTION WORK IN PROGRESS. I OBSERVED A 4409 LB JEKKO | Jul 16, 2018 | Found in violation | — |
| 035331248H | May 12, 2018 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Jul 17, 2018 | Found in violation | — |
| 035331247X | May 12, 2018 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AMENDMENTS | Jul 16, 2018 | Found in violation | — |
| 035317628Z | Feb 8, 2018 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Jun 1, 2018 | Found in violation | — |
| 1450355 | Feb 8, 2018 | 3303.6.1 ESCAPE HATCH-REQUIRED LADDERS AND METAL SHIELD NOTE: AT THE TIME OF MY INSPECTION OF A 30 STORY BUILDING AT 7TH FLOOR LEVEL CONSTRUCTION WORK IN PROGRESS THAT REQUIRE PORTABLE FUEL FIRE HEATERS ON SIX | Jun 1, 2018 | Found in violation | — |
| 035317625N | Feb 8, 2018 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | Jun 1, 2018 | Found in violation | — |
| 1450357 | Feb 8, 2018 | STORAGE NEAR UNENCLOSED PERIMETER. NOTE: AT THE TIME OF MY INSPECTION OF A 30 STORY BUILDING AT THE 7TH FLOOR LEVEL, CONSTRUCTION WORK IN PROGRESS.I OBSERVED THAT THERE WERE NO VERTICAL NETTING PROVIDED FOR | Jun 1, 2018 | Found in violation | — |
| 1414627 | Feb 8, 2018 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND OR APPROVED DOCUMENTS .NOTE AT THE TIME OF MY INSPECTION OF A 30 STORY BUILDINGAT THE 8TH FLOOR LEVEL,CONSTRUCTION WORK IN PROGRESS. I OBSERVED A | Jun 1, 2018 | Found in violation | — |
| 035317629K | Feb 8, 2018 | MISCELLANEOUS VIOLATIONS | Jun 1, 2018 | Found in violation | — |
| 035317627R | Feb 8, 2018 | MISCELLANEOUS VIOLATIONS | Jun 1, 2018 | Found in violation | — |
| 1450356 | Feb 8, 2018 | FAILURE TO INSTITUTE AND MAINTAIN SAFETY EQUIPMENT MEASURES AND TEMP ORARY CONSTRUCTION.NOTE: AT THE TIME OF MY INSPECTION OF A 30 STORY BUILDING AT 7TH FLOOR LEVEL CONSTRUCTION WORK IN PROGRESS I OBSERVED | Jun 1, 2018 | Found in violation | — |
| 035224988J | May 16, 2017 | MISCELLANEOUS VIOLATIONS | Aug 28, 2017 | Found in violation | — |
| 91575 | May 16, 2017 | BC3301.1.2/FAILURE TO COMPLY WITH NYC FIRE CODE.NO FIRE SAFETY MANAGERON SITE.30 STORY NEW BUILDING UNDE CONSTRUCTION WITH TORCH AND COMPRESSED FLAMMABLE GASES ON SITE AS WELL AS WELDING BEING PERFORMED NO LOOP | Aug 28, 2017 | Found in violation | — |