Open ViolationsA public record project
/

D26-16.03 Adm Code Repair The Broken Or Defective Rain

HPD order 652 · cites NYC Housing Maintenance Code § 27-2027 · written Mar 18, 1976Jun 17, 2026

HPD has written 1,105 violations under order 652, "D26-16.03 Adm Code Repair The Broken Or Defective Rain", citing NYC Housing Maintenance Code § 27-2027. 398 are open right now, 391 of them past the legal deadline on the notice.

Open now
398
Open past deadline
391
Closed
707
All time
1,105
Class C (immediately hazardous)
0

How order 652 is actually enforced

  • 32 notices (2.9%) sit at not complied with: the deadline passed and HPD found the condition unrepaired.
  • 5 certifications of repair were rejected by HPD. 1 of those are recorded as false certification: the owner certified a repair that inspection did not confirm.
  • 6 repairs were certified after the deadline.
  • 563 notices (51.0%) are reissues: the violation was written, not fixed, and written again.
  • 126 notices (11.4%) were dismissed.

Open order-652 violations by borough

BROOKLYN218
QUEENS76
MANHATTAN44
BRONX42
STATEN ISLAND18

The law behind this order

Order 652is HPD’s standard wording for one kind of condition. The legal duty it enforces is NYC Housing Maintenance Code § 27-2027, "Drainage of roofs and court yards". The section page carries the statute text, the measured cure times and the full enforcement record.

§ 27-2027 Drainage of roofs and court yards · Browse open § 27-2027 records in the live feed · All violation codes

Counted from HPD’s Housing Maintenance Code Violations dataset by order number. Figures recomputed Aug 5, 2026.