HPD order 853 · cites NYC Housing Maintenance Code § 27-2010 · written May 15, 2000Jul 27, 2026

HPD has written 1,249 violations under order 853, "Cleanse To The Satisfaction Of This Department The Ceramic", citing NYC Housing Maintenance Code § 27-2010. 801 are open right now, 742 of them past the legal deadline on the notice.

Open now
801
Open past deadline
742
Closed
448
All time
1,249
Class C (immediately hazardous)
0

How order 853 is actually enforced

  • 29 notices (2.3%) sit at not complied with: the deadline passed and HPD found the condition unrepaired.
  • 23 certifications of repair were rejected by HPD. 3 of those are recorded as false certification: the owner certified a repair that inspection did not confirm.
  • 6 repairs were certified after the deadline.
  • 163 notices (13.1%) are reissues: the violation was written, not fixed, and written again.
  • 164 notices (13.1%) were dismissed.

Open order-853 violations by borough

BROOKLYN377
QUEENS178
BRONX127
STATEN ISLAND117
MANHATTAN2

The law behind this order

Order 853is HPD’s standard wording for one kind of condition. The legal duty it enforces is NYC Housing Maintenance Code § 27-2010, "Cleaning of roofs, yards, courts and other open spaces". The section page carries the statute text, the measured cure times and the full enforcement record.

§ 27-2010 Cleaning of roofs, yards, courts and other open spaces · Browse open § 27-2010 records in the live feed · All violation codes