| 967577 | May 29, 2026 | FAILURE TO PROVIDE UNOBSTRUCTED EXIT PASSAGEWAY. AT TIME OF INSPECTION | Aug 4, 2026 | PENDING | $2,500.00 |
| 967585 | May 29, 2026 | FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: USE OF PROHIBIT | Aug 4, 2026 | PENDING | $1,250.00 |
| 764829 | Feb 7, 2023 | BC907.2.8 FAILURE TO PROVIDE CLASS "J" FIRE ALARM SYSTEM FOR TRANSIENT | Sep 12, 2023 | IN VIOLATION | — |
| 764570 | Feb 7, 2023 | PERMANENT DWELLING USED/CONVERTED FOR OTHER THAN PERMANENT-RESIDENTIAL | Sep 12, 2023 | IN VIOLATION | — |
| 1532851 | Mar 27, 2022 | I OBSERVED AN EQUIPMENT STORAGE AREA ALONG VERNON BOULEVARD WITH STEEL | May 17, 2022 | ADMIT/IN-VIO | — |
| 75996 | Jun 11, 2021 | FAILURE TO COMMUNICATE REQUIRED INFORMATION TO WORKER DURING PRE-SHIFT | Aug 31, 2021 | ADMIT/IN-VIO | — |
| 1559233 | Jun 11, 2021 | SEC. BC 3301.13.13 FAILURE TO HAVE OR MAINTAIN THE REQUIRED DAILY LOG. | Aug 31, 2021 | ADMIT/IN-VIO | — |
| 1505333 | May 14, 2021 | FAILURE TO NOTIFY DEPT OF ACCIDENT/INCIDENT THAT RESULTED IN FATALITY | Oct 26, 2021 | IN VIOLATION | — |
| 1532094 | Apr 30, 2021 | INADEQUATE SCAFFOLD SYSTEM.AT THE TIME OF MY INSPECTION OF AN ACTIVE 8 | Jul 20, 2021 | ADMIT/IN-VIO | — |
| 1553007 | Apr 30, 2021 | 3308.5 GUARD RAIL NETING.NOTE:AT THE TIME OF MY INSPECTION OF AN ACTIV | Jul 20, 2021 | ADMIT/IN-VIO | — |
| 1428461 | Apr 29, 2021 | A CONSTRUCTION SUPERINTENDENT FAILED TO PERFORM DUTIES AS PER RULE.THE | Aug 3, 2021 | ADMIT/IN-VIO | — |
| 1428455 | Apr 29, 2021 | FAILURE TO PROVIDE EVIDENCE OF SCISSORS LIFT TRAINING CARD IN ACCORDAN | Jul 20, 2021 | ADMIT/IN-VIO | — |
| 1428447 | Apr 29, 2021 | 3301.8.1 TAMPERING W/EVIDENCE.AT THE TIME OF MY RESPONSE TO AN INCIDEN | Jul 20, 2021 | ADMIT/IN-VIO | — |
| 1605046 | Apr 29, 2021 | FAILURE TO INSTITUTE AND MAINTAIN SAFETY EQUIPMENT MEASURES.NOTE:AT TH | Aug 3, 2021 | ADMIT/IN-VIO | — |
| 1556211 | Apr 13, 2020 | JOBSITE FENCE.NOTE:AT THE TIME OF MY INSPECTION,I OBSERVED THAT APPROX | Nov 10, 2020 | IN VIOLATION | — |
| 035411190Y | Feb 6, 2020 | SUPERVISION OR USE OF POWER-OPERATED HOISTING MACHINE W O LICENSE | Mar 2, 2021 | IN VIOLATION | — |
| 1534338 | Feb 6, 2020 | AT TIME OF INSPECTION SUPERVISION OR USE OF POWER OPERATED HOISTING MA | Mar 2, 2021 | IN VIOLATION | — |
| 035413718M | Jul 15, 2019 | FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER | Sep 24, 2019 | STIPULATED | — |
| 0206611580 | Dec 30, 2018 | DIRTY SIDEWALK DIRTY AREA | Feb 25, 2019 | SETTL IN-VIO | — |
| 0205249743 | Oct 10, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Nov 21, 2018 | SETTL IN-VIO | — |
| 0204013646 | Jun 29, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Aug 6, 2018 | SETTL IN-VIO | — |
| 0204013600 | Jun 18, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Jul 30, 2018 | SETTL IN-VIO | — |
| 0204013527 | May 7, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Jun 25, 2018 | SETTL IN-VIO | — |
| 0197256869 | Apr 4, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Jun 18, 2018 | SETTL IN-VIO | — |
| 0197256988 | Feb 18, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Mar 26, 2018 | SETTL IN-VIO | — |
| 0197256813 | Jan 14, 2018 | FAILURE TO CLEAN 18 INCHES INTO STREET | Feb 23, 2018 | SETTL IN-VIO | — |
| 035294829X | Nov 19, 2017 | JOB SITE FENCE NOT CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION | Jan 9, 2018 | SETTL IN-VIO | — |
| 0195139194 | Nov 1, 2017 | FAILURE TO CLEAN 18 INCHES INTO STREET | Dec 11, 2017 | SETTL IN-VIO | — |
| 0195139167 | Oct 14, 2017 | FAILURE TO CLEAN 18 INCHES INTO STREET | Nov 27, 2017 | SETTL IN-VIO | — |
| 0195139240 | Sep 22, 2017 | FAILURE TO CLEAN 18 INCHES INTO STREET | Oct 30, 2017 | SETTL IN-VIO | — |
| 1464061 | Aug 3, 2007 | USE OR INSTALLATION OF PLUMBING MATERIALS OR EQUIPMENT WHICH DO NOT CO | Mar 25, 2008 | DEFAULT | — |
| 0154232257 | May 9, 2007 | DIRTY SIDEWALK DIRTY AREA | Jun 20, 2007 | DEFAULTED | — |