61-27 186 Street at a glance
61-27 186 Street, Queens has 9 open city records on file, none of them Class C, and $32,520.00 recorded as due on OATH/ECB summonses. The most recent record is dated May 28, 2026.
Open Class C
0
Immediately hazardous
Open Class B
8
Hazardous
Open Class A
1
Non-hazardous
Fines due
$32,520.00
Balance on OATH/ECB summonses
Permits on file
65
DOB permit records
Last activity
May 28, 2026
DOB record
Health score for 61-27 186 Street
A composite of public indicators. Every input is a public record. See the full methodology.
C
Health score · Aug 4, 2026
Scored from the 300 most recent of 356 public records for this building
Open Class C violations
Immediately hazardous, uncertified
This building 0
Open Class B violations
Hazardous
This building 8
Heat & hot water records
Violations and complaints, last 24 months
This building 0
Unpaid penalties
OATH/ECB summonses with balance due
This building $32,520
Bedbug filings with infestations
Annual LL69 filings on record
This building 0
Tenant litigation
Open HP actions in Housing Court
This building 0
Active vacate order
HPD or FDNY order to vacate, still in effect
This building No
Record timeline for 61-27 186 Street
Records from every agency, interleaved. Showing the 300 most recent of 356 records on file; the CSV below has the full history.
May 28, 2026
May 8, 2026
Apr 20, 2026
Apr 20, 2026
Mar 12, 2026
Feb 3, 2026
Nov 21, 2025
Oct 28, 2025
Oct 15, 2025
Oct 2, 2025
Aug 1, 2025
Jul 23, 2025
Jun 30, 2025
Jun 30, 2025
Jun 24, 2025
Jun 22, 2025
Jun 21, 2025
Jun 20, 2025
Jun 16, 2025
Jun 16, 2025
Jan 22, 2025
Dec 2, 2024
Aug 3, 2024
Jun 5, 2024
Jun 5, 2024
May 29, 2024
May 29, 2024
May 3, 2024
Apr 18, 2024
Apr 18, 2024
OATH / ECB summonses & fines at 61-27 186 Street
$32,520.00 is recorded as due across the 124 summonses below, out of $239,925.00 in penalties imposed. The city’s published records do not show whether a penalty was paid, reduced, or written off.
| 269293 | Apr 20, 2026 | FAILURE TO FILE ACCEPTABLE CYCLE 9A REPORT INDICATING CORRECTION OF UN | Aug 11, 2026 | PENDING | $1,250.00 |
| 037036948J | Apr 20, 2026 | FAIL TO FILE AMENDMENT ACCEPTABLE REPORT TO CORRECT UNSAFE CONDITIONS | Aug 11, 2026 | NONE | $1,250.00 |
| 012179282N | Mar 12, 2026 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Jun 22, 2026 | DEFAULTED | $5,000.00 |
| 012172982M | Oct 15, 2025 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Dec 15, 2025 | DEFAULTED | $5,000.00 |
| 012166880K | Jun 16, 2025 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Aug 4, 2025 | DEFAULTED | $5,000.00 |
| 012165629X | Jan 22, 2025 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Jul 7, 2025 | DEFAULTED | $1,000.00 |
| 048277758P | Apr 5, 2024 | SPILLAGE FROM A RECEPTACLE 1ST OFFENSE | Jul 5, 2024 | DEFAULTED | $100.00 |
| 012148319X | Dec 23, 2023 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | May 6, 2024 | DEFAULTED | $5,000.00 |
| 012142771P | Oct 30, 2023 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Feb 5, 2024 | DEFAULTED | — |
| 1710462 | Feb 2, 2023 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS.NOT | Jan 16, 2024 | DEFAULT | $4,460.00 |
| 035670386M | Feb 2, 2023 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Jan 16, 2024 | DEFAULTED | $4,460.00 |
| 1646257 | Dec 20, 2022 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS. NO | Feb 28, 2023 | IN VIOLATION | — |
| 035669460N | Dec 20, 2022 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Feb 28, 2023 | IN VIOLATION | — |
| 1680719 | Dec 2, 2022 | FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE9A REPORT OF CRITICAL EXAM | May 16, 2023 | DEFAULT | — |
| 037024096K | Dec 2, 2022 | FAIL SUBMIT REQUIRED REPORT OF CRIT EXAM DOCUMENTING EXTERIOR WALL | May 16, 2023 | DEFAULTED | — |
| 0208001833 | Jan 28, 2022 | DEFACEMENT OF ROADWAY OR SIDEWALK | Apr 27, 2022 | SETTL IN-VIO | — |
| 012102189N | Aug 14, 2020 | FIRE PROTECTION SYSTEMS:FAIL TO PREVENT UNNECESSARY UNWARRANTED ALARMS | Dec 7, 2020 | IN VIOLATION | — |
| 1268706 | May 3, 2017 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS &/OR APPROVED | Sep 26, 2017 | IN VIOLATION | — |
| 035184560P | May 3, 2017 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AMENDMENTS | Sep 26, 2017 | IN VIOLATION | — |
| 1184781 | Oct 25, 2016 | TEMPORARY CONSTRUCTION EQUIPMENT IN SITE-EXPIRED PERMIT @TIME OF INSPE | Dec 13, 2016 | IN VIOLATION | — |
| 035163006P | Oct 25, 2016 | TEMPORARY CONSTRUCTION EQUIPMENT ON SITE-EXPIRED PERMIT | Dec 13, 2016 | IN VIOLATION | — |
| 1156748 | Sep 28, 2016 | PARTIAL STOP WORK ORDER FOR SUPPORTED SCAFFOLD ISSUED PURSUANT TO 28- | Nov 15, 2016 | IN VIOLATION | — |
| 035199634K | Sep 28, 2016 | MISCELLANEOUS VIOLATIONS | Nov 15, 2016 | IN VIOLATION | — |
| 1185474 | Sep 10, 2016 | 3308.3 VERTICAL NETTING NOT PER CODE, DAMAGED OR INADEQUATE.AT TIME OF | Oct 25, 2016 | IN VIOLATION | — |
| 1185472 | Sep 10, 2016 | MISSING/INADEQUATE GUARD RAILS AT TIME OF INSPECTION OBSERVED A NEW BL | Oct 25, 2016 | IN VIOLATION | — |
| 035206834H | Sep 10, 2016 | MISCELLANEOUS VIOLATIONS | Oct 25, 2016 | IN VIOLATION | — |
| 035206832Y | Sep 10, 2016 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT ETC.,- NO GUARD RAILS | Oct 25, 2016 | IN VIOLATION | — |
| 911242 | Aug 11, 2016 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION CONSTRUCTION DOCUMENTS | Sep 27, 2016 | IN VIOLATION | — |
| 035162945Z | Aug 11, 2016 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT MEASURES - NO TOE BOARD | Sep 27, 2016 | IN VIOLATION | — |
| 035162946K | Aug 11, 2016 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT ETC.,- NO GUARD RAILS | Sep 27, 2016 | IN VIOLATION | — |
| 035162947M | Aug 11, 2016 | MISCELLANEOUS VIOLATIONS | Sep 27, 2016 | IN VIOLATION | — |
| 911359 | Aug 11, 2016 | FAILURE TO INSTITUTE SAFETY EQUIPMENT MEASURES OR TEMPORARY CONSTRUCTI | Sep 27, 2016 | IN VIOLATION | — |
| 1184778 | Aug 11, 2016 | FAILURE TO INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY C | Sep 27, 2016 | IN VIOLATION | — |
| 035162948Y | Aug 11, 2016 | WORK WITHOUT A PERMIT | Sep 26, 2016 | STIPULATED | — |
| 1131817 | Aug 11, 2016 | WORK W/OUT A PERMIT. EXPIRED PERMIT. @ TIME OF INSP OF A 12 STORY NEW | Sep 26, 2016 | STIPULATION/IN-VIO | — |
| 1184779 | Aug 11, 2016 | SEC. 28-110.1 OSHA 10. AT TIME OF INSPECTION OF 12 STY NEW BLDG UNDER | Sep 27, 2016 | IN VIOLATION | — |
| 035162944R | Aug 11, 2016 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | Sep 27, 2016 | IN VIOLATION | — |
| 035195951X | Jul 16, 2016 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | Aug 30, 2016 | IN VIOLATION | — |
| 1166023 | Jul 16, 2016 | FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY CONSTRUCTION O | Aug 30, 2016 | IN VIOLATION | — |
| 035195810M | Jul 1, 2016 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Oct 4, 2016 | IN VIOLATION | — |
| 1185222 | Jul 1, 2016 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS AT | Oct 4, 2016 | IN VIOLATION | — |
| 035195809P | Jul 1, 2016 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT ETC.,- NO GUARD RAILS | Oct 4, 2016 | IN VIOLATION | — |
| 1185221 | Jul 1, 2016 | FAILURE TO INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY | Oct 4, 2016 | IN VIOLATION | — |
| 1185220 | Jul 1, 2016 | FAILURE TO FILE EVIDENCE OF COMPLIANCE WITH WORKERS COMP LAW OR AND DI | Oct 4, 2016 | IN VIOLATION | — |
| 035178614K | Mar 24, 2016 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | May 10, 2016 | IN VIOLATION | — |
| 035178617X | Mar 24, 2016 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | May 10, 2016 | IN VIOLATION | — |
| 1105362 | Mar 24, 2016 | 3301.7 DESIGN: REQUIRED/CONTRARY. NOTE: ACTIVE SITE, SUPPORTED SCAF | May 10, 2016 | IN VIOLATION | — |
| 547841 | Mar 24, 2016 | SEC. 3314.4.3 INSPECTIONS: SUPPORTED SCAFFOLD. NOTE: ACTIVE JOBSITE,SU | May 10, 2016 | IN VIOLATION | — |
| 547832 | Mar 24, 2016 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS &/OR AMENDMEN | May 10, 2016 | IN VIOLATION | — |
| 548061 | Mar 24, 2016 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | May 10, 2016 | IN VIOLATION | — |
| 035178615M | Mar 24, 2016 | MISCELLANEOUS VIOLATIONS | May 10, 2016 | IN VIOLATION | — |
| 035178616Y | Mar 24, 2016 | MISCELLANEOUS VIOLATIONS | May 10, 2016 | IN VIOLATION | — |
| 1157584 | Jan 26, 2016 | 3314.1.1 PARTIAL STOP WORK ORDER FOR SUPPORTED SCAFOFLD ISSUED PURSUAN | Mar 15, 2016 | STIPULATION/IN-VIO | — |
| 035157789J | Jan 26, 2016 | MISCELLANEOUS VIOLATIONS | Mar 15, 2016 | STIPULATED | — |
| 035162378L | Dec 9, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AMENDMENTS | Jan 26, 2016 | IN VIOLATION | — |
| 455811 | Dec 9, 2015 | WOK DOES NOT CONFORM TO APPROVED CONST DOCS &/OR APPROVED AMENDMENTS.N | Jan 26, 2016 | IN VIOLATION | — |
| 035162377J | Dec 9, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | Jan 26, 2016 | IN VIOLATION | — |
| 035162379N | Dec 9, 2015 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Jan 26, 2016 | IN VIOLATION | — |
| 1136714 | Dec 9, 2015 | FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY CONST OPS.NOTE | Jan 26, 2016 | IN VIOLATION | — |
| 1136715 | Dec 9, 2015 | FAILURE TO MAINTAIN:HOUSEKEEPING.NOTE:ACTIVE JOBSITE, 11 FL FORMWORK R | Jan 26, 2016 | IN VIOLATION | — |
| 035161690L | Nov 2, 2015 | MISCELLANEOUS VIOLATIONS | Dec 22, 2015 | IN VIOLATION | — |
| 1138430 | Nov 2, 2015 | 28-110.1 OSHA 10.AT TIME OF RE-INSPECTION OF 12 STORY PR0POSED NEW BUI | Dec 22, 2015 | IN VIOLATION | — |
| 1095693 | Sep 22, 2015 | SEC. 3310.6 DESIGNATED SITE SAFETY MANAGER. AT TIME OF INSPECTION NOTE | Nov 10, 2015 | ADMIT/IN-VIO | — |
| 035160271M | Sep 22, 2015 | MISCELLANEOUS VIOLATIONS | Jan 28, 2016 | IN VIOLATION | — |
| 1125798 | Sep 22, 2015 | SUBMITTAL OF CONSTRUCTION DOCUMENTS. AS NOTED: AT TIME OF INSPECTION | Nov 17, 2015 | IN VIOLATION | — |
| 1110684 | Sep 22, 2015 | SEC. 3310.2(E)(G)FAILURE OF CONCRETE SAFETY MANAGER TO PERFORM REQUIRE | Jan 28, 2016 | IN VIOLATION | — |
| 1095691 | Sep 22, 2015 | SEC. 3307.3 OVERHEAD PROTECTION NOT PROVIDED. AT TIME OF INSPECTION NO | Nov 10, 2015 | ADMIT/IN-VIO | — |
| 1125623 | Sep 22, 2015 | FAILURE TO SAFEGUARD PUBLIC & PROPERTY. AT TIME OF INSPECTION NOTED TH | Nov 10, 2015 | ADMIT/IN-VIO | — |
| 035146039R | Sep 22, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | Nov 10, 2015 | Pending | — |
| 035146042H | Sep 22, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | Nov 10, 2015 | Pending | — |
| 035146040Y | Sep 22, 2015 | MISCELLANEOUS VIOLATIONS | Nov 10, 2015 | Pending | — |
| 035160261Z | Sep 22, 2015 | MISCELLANEOUS VIOLATIONS | Nov 17, 2015 | IN VIOLATION | — |
| 1110685 | Sep 22, 2015 | SEC. 3310.9.1 CONCRETE SAFETY MANAGER(EXPIRED LIC REGISTRATION)AS NOTE | Jan 28, 2016 | IN VIOLATION | — |
| 035160272Y | Sep 22, 2015 | MISCELLANEOUS VIOLATIONS | Jan 28, 2016 | IN VIOLATION | — |
| 1102894 | Aug 18, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV | Oct 6, 2015 | ADMIT/IN-VIO | — |
| 901117 | Aug 18, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Oct 6, 2015 | ADMIT/IN-VIO | — |
| 035145474R | Aug 18, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Oct 6, 2015 | Pending | — |
| 035145425K | Aug 18, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AMENDMENTS | Oct 6, 2015 | Pending | — |
| 035145352Z | Aug 6, 2015 | USE OF SUPPORTED SCAFFOLD WITHOUT A SCAFFOLD USER CERTIFICATE | Oct 27, 2015 | IN VIOLATION | — |
| 035145353K | Aug 6, 2015 | MISCELLANEOUS VIOLATIONS | Oct 27, 2015 | IN VIOLATION | — |
| 326249 | Aug 6, 2015 | 3301.2 FAILURE TO PROVIDE ADEQUATE MEANS OF EGRESS.BOTH STAIRWAYS ARE | Oct 27, 2015 | IN VIOLATION | — |
| 326139 | Aug 6, 2015 | WORKERS (APPROVE 4) WERE OBSERVED REMOVING PLANKS FROM SUPPORTED SCAF | Oct 27, 2015 | IN VIOLATION | — |
| 326113 | Aug 6, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS/DESIGN DRAW | Oct 27, 2015 | IN VIOLATION | — |
| 035145350P | Aug 6, 2015 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | Oct 27, 2015 | IN VIOLATION | — |
| 326121 | Aug 6, 2015 | UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER.PARTIAL | Oct 27, 2015 | IN VIOLATION | — |
| 035145351R | Aug 6, 2015 | UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER | Oct 27, 2015 | IN VIOLATION | — |
| 898831 | Jul 31, 2015 | 3314.1 PARTIAL STOP WORK ORDER FOR SUPPORTED SCAFFOLD ISSUED PURSUANT | Sep 15, 2015 | IN VIOLATION | — |
| 035132878K | Jul 31, 2015 | MISCELLANEOUS VIOLATIONS | Sep 15, 2015 | IN VIOLATION | — |
| 673983 | May 21, 2015 | FAILURE TO MAINTAIN.NO GUARDRAILS.AT TIME OF INSPECTION OBSERVED ACTIV | Oct 6, 2015 | IN VIOLATION | — |
| 673967 | May 21, 2015 | 3301.7. DESIGN REQUIRED BY CHAPTER 33-MATERIAL HOIST. AT TIME OF INSPE | Oct 6, 2015 | IN VIOLATION | — |
| 673997 | May 21, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV | Oct 6, 2015 | IN VIOLATION | — |
| 035130886L | May 21, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROP AFFECTED BY CONST OPERATIONS | Oct 6, 2015 | IN VIOLATION | — |
| 035130888P | May 21, 2015 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT ETC.,- NO GUARD RAILS | Oct 6, 2015 | IN VIOLATION | — |
| 035130889R | May 21, 2015 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Oct 6, 2015 | IN VIOLATION | — |
| 035130891X | May 21, 2015 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | Oct 6, 2015 | IN VIOLATION | — |
| 673951 | May 21, 2015 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Oct 6, 2015 | IN VIOLATION | — |
| 035130887N | May 21, 2015 | MISCELLANEOUS VIOLATIONS | Oct 6, 2015 | IN VIOLATION | — |
| 673993 | May 21, 2015 | FAILURE TO MAINTAIN HOUSEKEEPING.AT TIME OF INSPECTION OBSERVED ACTIVE | Oct 6, 2015 | IN VIOLATION | — |
| 677186 | May 2, 2015 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV | Jul 7, 2015 | DEFAULT | — |
| 035130885J | May 2, 2015 | WORK DOES NOT CONFORM TO APPROVED CONST. DOCUMENTS AND OR APPROVED AME | Jul 7, 2015 | DEFAULT | — |
| 1703003 | Dec 18, 2014 | 3313.1,COMBUSTIBLE LIQUID NOT STORED PROPERLY.NOTICED @ TIME OF INSP N | Feb 3, 2015 | IN VIOLATION | — |
| 1702987 | Dec 18, 2014 | FAILURE TO SAFEGUARD NOTICE AT TIME OF INSPECTION NB IN PROGRESS PAV | Feb 3, 2015 | IN VIOLATION | — |
| 035121711P | Dec 18, 2014 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Feb 3, 2015 | IN VIOLATION | — |
| 035121712R | Dec 18, 2014 | MISCELLANEOUS VIOLATIONS | Feb 3, 2015 | IN VIOLATION | — |
| 035109833L | Oct 9, 2014 | WORK WITHOUT A PERMIT | Nov 25, 2014 | IN VIOLATION | — |
| 1021913 | Oct 9, 2014 | WORK W/O A PERMIT. SIDEWALK SHED. AT TIME OF INSPECTION OBSERVED ACTIV | Nov 25, 2014 | IN VIOLATION | — |
| 035098653N | Jul 17, 2014 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT ETC.,- NO GUARD RAILS | Sep 2, 2014 | IN VIOLATION | — |
| 934189 | Jul 17, 2014 | FAILURE TO SAFEGUARD ALL PERSON & PROPERTY AFFECTED BY CONSTRUCTION OP | Sep 2, 2014 | IN VIOLATION | — |
| 035098654P | Jul 17, 2014 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | Sep 2, 2014 | IN VIOLATION | — |
| 1067732 | Jul 17, 2014 | FAILURE TO INSTITUTE MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY C | Sep 2, 2014 | IN VIOLATION | — |
| 1067737 | Jul 17, 2014 | FAILURE TO MAINTAIN ADEQUATE LIGHTING IN WORK AREA NOTE AT TIME OF INS | Sep 2, 2014 | IN VIOLATION | — |
| 035098655R | Jul 17, 2014 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS | Sep 2, 2014 | IN VIOLATION | — |
| 934124 | Jul 3, 2014 | NO CONCRETE SAFETY MANAGER PRESENT DURING ALL CONCRETE OPERATIONS AS R | Sep 23, 2014 | IN VIOLATION | — |
| 035098157Y | Jul 3, 2014 | NO CONCRETE SAFETY MANAGER PRESENT DURING ALL CONCRETE OPER.AS REQUIRE | Sep 23, 2014 | IN VIOLATION | — |
| 652178 | Jun 10, 2014 | 3303.1.3 COMBUSTIBLE SHED LOCATED @ CELLAR LEVEL OF ACTIVE CONS JOB.@ | Oct 7, 2014 | IN VIOLATION | — |
| 035092647J | Jun 10, 2014 | MISCELLANEOUS VIOLATIONS | Oct 7, 2014 | IN VIOLATION | — |
| 907833 | Jun 9, 2014 | 3303.4.1,FAILURE TO MAINTAIN SIDEWALK(FREE)FROM EQUIPMENT.AS NOTED:@ T | Oct 7, 2014 | IN VIOLATION | — |
| 034904510N | Jun 9, 2014 | MISCELLANEOUS VIOLATIONS | Oct 7, 2014 | IN VIOLATION | — |
| 932766 | May 14, 2014 | FAILURE TO PROVIDE TEMPORARY WALKWAY. AT TIME OF INSPECTION OBSERVED A | Sep 25, 2014 | IN VIOLATION | — |
| 932737 | May 14, 2014 | NO CONCRETE SAFETY MANAGER PRESENT DURING ALL CONCRETE OPERATIONS AS R | Sep 25, 2014 | IN VIOLATION | — |
| 035087029X | May 14, 2014 | MISCELLANEOUS VIOLATIONS | Sep 25, 2014 | IN VIOLATION | — |
| 035087028Y | May 14, 2014 | MISCELLANEOUS VIOLATIONS | Sep 25, 2014 | IN VIOLATION | — |
| 035087027M | May 14, 2014 | NO CONCRETE SAFETY MANAGER PRESENT DURING ALL CONCRETE OPER.AS REQUIRE | Sep 25, 2014 | IN VIOLATION | — |
| 932763 | May 14, 2014 | 3303.4.5.3 PRECAUTIONS TO PREVENT CONCRETE WASHING,SAND,GRIT MATERIAL | Sep 25, 2014 | IN VIOLATION | — |