| 1632584 | Jan 25, 2022 | FAILURE TO MAINTAIN BLDG WALLS OR APPURTENANCES.OBSERVE LOOSE METAL CO | Jun 8, 2022 | IN VIOLATION | — |
| 394568 | Sep 4, 2014 | 3303.2.4,FAILURE TO HAVE SANITARY FACILITIES CLEAN & ADQUATE FOR USE B | Oct 23, 2014 | IN VIOLATION | — |
| 650106 | Sep 4, 2014 | SEC. 3307.4.3 FAILURE TO COMPLY W/DEPT RULES & REGULATION FOR LANE CLO | Oct 20, 2014 | IN VIOLATION | — |
| 1043634 | Jun 4, 2014 | WORK W/O PERMIT. OBSERVED MEN WORKING ON SUPPORTED SCAFFOLD ( 5 TIERS | Jul 21, 2014 | IN VIOLATION | — |
| 576009 | Jun 4, 2014 | USE OF SUPPORTED SCAFFOLD W/O A SCAFFOLD USER CERTIFICATE. NOTED : 4 W | Jul 30, 2014 | IN VIOLATION | — |
| 575906 | Jun 4, 2014 | INADEQUTE GUARD RAIL. OBSERVED INADEQUATE GUARD RAIL INSTALLED AT ROOF | Jul 30, 2014 | IN VIOLATION | — |
| 1004785 | Apr 7, 2014 | FAILURE TO SAFEGUARD ALL PERSONS&PROERPTY AFFECTED BY CONST OPS.INADEQ | Aug 11, 2014 | IN VIOLATION | — |
| 1023061 | Apr 18, 2013 | SEC. BC 3301.7. DESIGN DRAWING REQUIRED BY THE PROVISION OF CHAPTER 33 | Aug 7, 2013 | IN VIOLATION | — |
| 1001033 | Apr 18, 2013 | USE OF SUPPORTED SCAFFOLD W/O A SCAFFOLD USER CERTIFICATE. AT NB UNDER | Jun 3, 2013 | IN VIOLATION | — |
| 573932 | Apr 18, 2013 | SEC. 2205.6.2. FIELD CONNECTIONS: NOTED: AT NEW BLDG W/STEEL FRAME CON | Jul 24, 2013 | IN VIOLATION | — |
| 917295 | Mar 30, 2013 | SEC. 3303.3. OBSTRUCTION OF SIDEWALK AND STREETS. NOTED: FAILURE TO MA | May 20, 2013 | IN VIOLATION | — |
| 930342 | Mar 30, 2013 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION | May 20, 2013 | IN VIOLATION | — |
| 1180187 | Oct 14, 2010 | WORK W/O A PERMIT EXPIRED PERMIT PLYWOOD CONSTRUCTION FENCE IN ACCORDA | May 2, 2011 | IN VIOLATION | — |
| 888525 | Dec 30, 2009 | FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY DEMOLITION OPE | Feb 22, 2010 | IN VIOLATION | — |
| 889145 | Oct 28, 2009 | FAIL TO PROVIDE POST SIGN AT JOB SITE PURSUANT TO SUBSECTION. UPON INS | Feb 23, 2011 | IN VIOLATION | — |
| 889175 | Oct 28, 2009 | SEC BC 3309.9 MISC VIOL: WEATHERPROOF INTEGRITY OF ADJOINING BLDG. UPO | Feb 23, 2011 | IN VIOLATION | — |
| 889210 | Oct 28, 2009 | JOB SITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION. UPON INSPECTION | Feb 23, 2011 | IN VIOLATION | — |
| 886747 | May 27, 2009 | JOBSITE FENCE NOT CONSTRUCTED PURSUANT TO SUBSECTION UPON INSPECTION A | Jun 23, 2010 | IN VIOLATION | — |
| 886750 | May 27, 2009 | FAILURE TO SAFEGUARD PUBLIC AND PROPERTY EFFECTED BY DEMOLITION OPERAT | Jun 23, 2010 | IN VIOLATION | — |
| 1206974 | Apr 16, 2009 | WORK W/O A PERMIT.EXPIRED PERMIT UPON INSPECTION AT THE ABOVE ADDRESS | Aug 25, 2010 | IN VIOLATION | — |
| 884278 | Dec 4, 2008 | SEC BC 3309.49 & 27-1026(D) WEATHER PROOF INTEGRITY OF ADJOINING BLDG | Apr 25, 2011 | IN VIOLATION | — |
| 882955 | Nov 12, 2008 | FAILURE TO SAFEGUARD ALL PERSON AND PROPERTY AFFECTED BY DEMOLITION OP | Aug 25, 2010 | IN VIOLATION | — |
| 882942 | Nov 12, 2008 | FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY DEMOLITION O | Aug 25, 2010 | IN VIOLATION | — |
| 882293 | Sep 16, 2008 | FAILURE TO INSTITUTE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY C | Nov 17, 2008 | IN VIOLATION | — |
| 882281 | Sep 16, 2008 | FAILURE TO CARRY OUT DEMOLITION OPERATIONS AS REQUIRED BY SECTION. AT | Nov 17, 2008 | IN VIOLATION | — |
| 882276 | Sep 16, 2008 | FAILURE TO SAFEGUARD PUBLIC & PROPERTY AFFECTED BY CONSTRUCTION OPERAT | Nov 17, 2008 | IN VIOLATION | — |