| 1570116 | Aug 18, 2021 | EXTERIOR WALLS ON EXPOSURE 4 FROM 1ST. TO 4TH. FLOOR WERE INSTALLED WI | Dec 22, 2021 | STIPULATION/IN-VIO | $630.00 |
| 1564495 | Jun 28, 2021 | 3309.10 PROTECTION OF ROOFS WHENEVER ANY BUILDING IS TO BE CONSTRUCTED | Feb 9, 2022 | IN VIOLATION | — |
| 1564500 | Jun 28, 2021 | FAILURE TO COMPLY W/MANUFACTURER SPECIFICATIONS W/PLASTIC TRAFFIC BARR | Feb 9, 2022 | IN VIOLATION | — |
| 1564496 | Jun 28, 2021 | FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENT. NOT | Feb 9, 2022 | IN VIOLATION | — |
| 1572004 | Mar 26, 2021 | OVERHEAD PROTECTION. NOTE: AT THE TIME OF MY INSPECTION OF A 4 STY NEW | Aug 4, 2021 | IN VIOLATION | — |
| 1572005 | Mar 26, 2021 | BC 3307.2.6 REQUIREMENTS FOR SIDEWALK,WALKWAY AND PATHWAYS. NOTE-AT TH | Aug 4, 2021 | IN VIOLATION | — |
| 1628385 | Mar 26, 2021 | GUARDRAILS. NOTE: AT THE TIME OF MY INSPECTION OF A 4 STY NEW BLDG CON | Aug 1, 2022 | IN VIOLATION | — |
| 165942 | Mar 26, 2021 | FAIL TO COMMINICATE & MAINTAIN A RECORD OF ORIENTATION PERFORM AT JOB | Aug 1, 2022 | IN VIOLATION | — |
| 166213 | Mar 26, 2021 | PRE-SHIFT SAFETY MEETING. NOTE: AT THE TIME OF MY INSPECTION OF A 4 ST | Aug 1, 2022 | IN VIOLATION | — |
| 1566941 | Nov 17, 2020 | FAILURE TO INSTITUTE & MAINTAIN SAFETY EQUIPMENT-OVERLOAD PROTECTION. | Jun 18, 2021 | IN VIOLATION | — |
| 1400632 | May 28, 2019 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VI | Jan 9, 2020 | IN VIOLATION | $6,250.00 |
| 975145 | May 28, 2019 | REMOVED OR DEFACED A WRITTEN POSTED VACATE ORDER.AT THE TIME OF INSPEC | Sep 23, 2019 | IN VIOLATION | $2,500.00 |
| 183700 | Mar 15, 2019 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35303885 | Aug 12, 2019 | IN VIOLATION | $710.00 |
| 1260319 | Dec 5, 2018 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35303885 | Jun 10, 2019 | DEFAULT | $5,000.00 |
| 1392885 | Oct 11, 2018 | FAILURE TO COMPLY W/ THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIO | Dec 31, 2018 | IN VIOLATION | $1,250.00 |
| 1433346 | Aug 24, 2018 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VI | Nov 5, 2018 | IN VIOLATION | $1,250.00 |
| 590515 | Jul 14, 2018 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO #3530388 | Nov 19, 2018 | IN VIOLATION | $1,250.00 |
| 1366789 | May 19, 2018 | FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VI | Sep 17, 2018 | IN VIOLATION | $1,250.00 |
| 1439957 | Mar 30, 2018 | UNLAWFUL ACTS. FAILURE TO COMPLY WITH AN ORDER OF THE COMMISSIONER. | Aug 20, 2018 | IN VIOLATION | $2,500.00 |
| 1401737 | Mar 22, 2018 | FAILURE TO SAFEGUARD ALL PERSONS & PROPERTY AFFECTED BY CONSTRUCTION O | Jul 9, 2018 | IN VIOLATION | — |
| 721512 | Apr 2, 2010 | FAILURE TO FILE C OF C WITH DOB PURSUANT TO 28-204.2FOR VIOLATION 3481 | Dec 30, 2010 | IN VIOLATION | — |
| 420283 | Nov 2, 2009 | OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERT OF OCCUPANCY OR DOB REC | Dec 20, 2010 | IN VIOLATION | — |