| 1354282 | Aug 25, 2021 | UNLAWFULLY CONTINUE WORK WHILE ON NOTICE OF A SWO. AT THE TIME OF RE-I | Apr 11, 2022 | IN VIOLATION | $5,000.00 |
| 1400824 | Jan 25, 2021 | NO MANUFACTURE SPECS FOR PUMP JACKS. AT THE TIME OF MY INSPECTION AT A | Nov 8, 2021 | IN VIOLATION | $2,500.00 |
| 1400694 | Jan 25, 2021 | WORK DOES NOT CONFORM TO APPROVED PLANS-PIPE SCAFFOLD. AT THE TIME OF | Nov 8, 2021 | IN VIOLATION | $1,250.00 |
| 1400826 | Jan 25, 2021 | WORK DOES NOT CONFORM TO APPROVED PLANS-STAIRS. AT THE TIME OF MY INSP | Nov 8, 2021 | IN VIOLATION | $2,500.00 |
| 1617550 | Oct 29, 2020 | FAILURE TO INSTITUE/MAINTAIN SAFETY EQUIPMENT MEASURES OR TEMPORARY CO | Mar 10, 2021 | IN VIOLATION | $2,500.00 |
| 1617547 | Oct 29, 2020 | WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROV | Mar 10, 2021 | IN VIOLATION | $625.00 |
| 1617549 | Oct 29, 2020 | BC 3301.6,DESIGN,SIZES AND CAPACITY OF MATERIALS.STRUCTURES,TEMPORARY- | Mar 10, 2021 | IN VIOLATION | $625.00 |
| 1615017 | Oct 29, 2020 | BC 3301.4,INSPECTION LOGS:INSPECTION OF ALL EQUIPMENTS SSHALL BE PERFO | Jul 26, 2021 | IN VIOLATION | $625.00 |
| 1617548 | Oct 29, 2020 | BC1704.3.4,FAILURE TO PROVIDE/MAINTAIN SPECIAL INSPECTION REPORT FOR C | Mar 10, 2021 | IN VIOLATION | $2,500.00 |
| 67354 | May 23, 2020 | FAILURE TO SAFEGUARD ALL PERSOSN AND PROPERTY AFFECTED BY CONSTRUCTION | Jun 4, 2021 | IN VIOLATION | $10,000.00 |
| 1388134 | Apr 10, 2020 | SEC. 3303.4.2 DUMSPTER CONTAINER. NOYTE: AT TIME OF MY INSPECTION OF A | Oct 22, 2020 | IN VIOLATION | $2,500.00 |
| 1388174 | Apr 2, 2020 | BC3303.4.2=CONTAINERS NOTE AT THE TIME OF MY INSPECTION OF A 4 STORY A | Oct 22, 2020 | IN VIOLATION | $625.00 |
| 1487716 | Nov 14, 2019 | HOUSE KEEPING NOTE AT TIME OF MY INSPECTION OF A BUILDING BRING RENOVA | Mar 8, 2022 | DEFAULT | $6,250.00 |
| 1305638 | Nov 14, 2019 | BC3303.7.2/FIRE EXTINGUISHERS;NOTE:AT TIME OF MY INSPECTION OF A BUILD | Sep 17, 2020 | DEFAULT | $6,250.00 |
| 1586898 | Nov 14, 2019 | MISSING GUARD RAILS.NOTE:AT TIME OF INSPECTION OF A 4 STY BLDG UNDER R | Sep 17, 2020 | DEFAULT | $12,500.00 |
| 425189 | Dec 24, 2018 | BC28-105.12.3/ADHERENCE TO DIAGRAM/DEFICIENT DRAWINGS-THE RESPONDENT I | Dec 6, 2021 | IN VIOLATION | $625.00 |
| 1655491 | Dec 24, 2018 | BC107.7.1/DEFICIENT DRAWINGS THE RESPONDENT IS THE APPLICANT OF RECORD | Dec 6, 2021 | IN VIOLATION | $625.00 |
| 425628 | Dec 24, 2018 | BC107.7.4/DEFICIENT DRAWINGS-THE RESPONDENT IS THE APPLICANT OF RECORD | Dec 6, 2021 | IN VIOLATION | $625.00 |
| 1392549 | Aug 20, 2018 | JOB ISTE FENCE NOT CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION. A | Nov 5, 2018 | IN VIOLATION | — |