12 open Class C$6,250.00 recorded as dueHPD registration valid
Export CSV
OverviewHealth scoreTimelineFinesOwner
Open Class C
12
Immediately hazardous
Open Class B
53
Hazardous
Open Class A
5
Non-hazardous
Fines due
$6,250.00
Balance on OATH/ECB summonses
Permits on file
74
DOB permit records
Last activity
Jun 10, 2026
DOB record

Building health score

A composite of public indicators. Every input is a public record. See the full methodology.

D
Health score · Jul 29, 2026
Scored from all 283 public records for this building
Open Class C violations
Immediately hazardous, uncertified
This building 12
Open Class B violations
Hazardous
This building 53
Heat & hot water records
Violations and complaints, last 24 months
This building 0
Unpaid penalties
OATH/ECB summonses with balance due
This building $6,250
Bedbug filings with infestations
Annual LL69 filings on record
This building 0
Tenant litigation
Open HP actions in Housing Court
This building 2
Active vacate order
HPD or FDNY order to vacate, still in effect
This building No

Unified timeline

Every record from every agency, interleaved. 283 records on file.

Download this timeline (CSV) →
Jun 10, 2026
Jun 2, 2026
Apr 2, 2026
Dec 24, 2025
Dec 3, 2025
Nov 14, 2025
Nov 14, 2025
Nov 14, 2025
Nov 14, 2025
Nov 14, 2025
Nov 14, 2025
Feb 14, 2025
Feb 9, 2025
Feb 9, 2025
Jan 3, 2025
Jan 3, 2025
Dec 30, 2024
Dec 23, 2024
Dec 23, 2024
Dec 20, 2024
Dec 1, 2024
Sep 23, 2024
Sep 23, 2024
Sep 23, 2024
Sep 23, 2024
Jun 23, 2024
Apr 22, 2024
Apr 22, 2024
Apr 16, 2024
Apr 11, 2024

OATH / ECB summonses & fines

$6,250.00 is recorded as due across the 21 summonses below, out of $76,630.00 in penalties imposed. The city’s published records do not show whether a penalty was paid, reduced, or written off.

OATH and ECB summonses for 98 Montague Street
1803814Apr 2, 2026FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES. NOTE: Aug 7, 2026PENDING$5,000.00
1799928Feb 14, 2025RESPONDING A COMPLAINT OBSERVED: SIDEWALK SHED INSTALLED AT EXPO# 1-3-Mar 24, 2026ADMIT/IN-VIO
1682676Dec 30, 2024NO UNDERSIDE LIGHTING. AT THE TIME OF MY INSPECTION OF A SIDE WALK SHDec 8, 2025IN VIOLATION
1679241Feb 24, 2024AT THE TIME OF INSPECTION I OBSERVED ON THE FIRST FLOOR/GROUND ARE NEWMay 1, 2024DEFAULT
122660Jan 16, 2024FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8B AND 9B REPORT INDICATING CApr 10, 2024DEFAULT
89617Jun 20, 2023FAILURE TO MAINTAIN BUILDING FACADE OR APPURTENANCES.NOTE:AT THE TIME Oct 6, 2023IN VIOLATION
1254468Apr 28, 2023FAILURE TO TAKE AND PROVIDE SAFETY MEASURES SIDEWALK SHED NETTING ETC Jan 19, 2024IN VIOLATION
1799671Apr 28, 2023FAILURE TO MAINTAIN EXTERIOR BUILDING FACADES AND APPURTENANCES.NOTED:Jan 19, 2024IN VIOLATION
1670479Oct 27, 2022AT THE TIME OF MY INSPECTION OF A 15 STORY BUILDING, I OBSERVED SIDEWAMar 1, 2023IN VIOLATION$1,250.00
1631774Aug 31, 2022I OBSERVED SIDEWALK SHED IN PLACE AT EXP. #1,3,4 WITH AN EXPIRED PERMIJan 4, 2023ADMIT/IN-VIO
1630207Jul 8, 2022TEMPORARY CONSTRUCTION EQUIPMENT ONSITE-(SWS)EXPIRED PERMIT.OBSERVED SDec 7, 2022ADMIT/IN-VIO
825653Jul 8, 2022PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS.NOTE:AT TIME ODec 7, 2022IN VIOLATION
1412638Oct 8, 2021FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8B & 9B REPORT INDICATING CORApr 13, 2022ADMIT/IN-VIO
1413259Jul 15, 2021PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS.NOTE AT TIME ONov 24, 2021ADMIT/IN-VIO
1469524Feb 3, 2021PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS AT THE TIME OFJun 16, 2021DEFAULT
1479687Jan 29, 2021FAILURE TO MAINTAIN BLDG IN A CODE COMPLIANT MANNER. NOTED: AT CORNER Jun 9, 2021ADMIT/IN-VIO
972544Oct 20, 2020FAILURE TO COMPLY W/ COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORMar 3, 2021IN VIOLATION
1529473Aug 10, 2020FAILURE TI TAKE REQUIRED MEASURES TO PROTECT PUBLIC FROM DOCUMENTED UNDec 23, 2020IN VIOLATION
1494678Aug 5, 2020AT TIME OF INSPECTION, 8 MALE WORKERS CONSTRUCTING A 300 LINEAR FOOT SDec 9, 2020ADMIT/IN-VIO
1514507May 27, 2020FAILURE TO TAKE REQUIRED MEASURES TO PROTECT PUBLIC FROM DOCUMENTED UNSep 30, 2020IN VIOLATION
1498424Oct 15, 2018B230 28-302.4:FAILURE TO SUBMIT A REQUIRED CYCLE 8B REPORT OF CRITICALOct 7, 2019IN VIOLATION