| 1830027 | Apr 20, 2026 | FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 6, 7A, 8A, AND 9A REPORT INDI | Jul 30, 2026 | PENDING | $1,250.00 |
| 1666873 | Dec 9, 2022 | FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 6,7A,8A,9A,REPORT OF CRITI | Mar 2, 2023 | IN VIOLATION | — |
| 343988 | Nov 4, 2022 | FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE & APPURTENANCES.NOTE:AT T | Jul 13, 2023 | IN VIOLATION | — |
| 1204958 | Jun 1, 2021 | FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE6,7A,8A REPORT OF CRITICAL | Oct 20, 2022 | IN VIOLATION | — |
| 1500012 | Apr 23, 2020 | FAILURE TO MAINTAIN BUILDING EXTERIOR WALLS/FACADES AND APPURTENANCES | Oct 29, 2020 | IN VIOLATION | — |
| 1204438 | Jan 22, 2020 | FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 6, 7A AND 8A REPORT OF | Oct 29, 2020 | IN VIOLATION | — |
| 1776679 | Nov 23, 2019 | FAILURE TO COMPLY W/ THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIO | Jan 30, 2020 | IN VIOLATION | — |
| 1698132 | Oct 9, 2019 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35375132 | Dec 19, 2019 | IN VIOLATION | — |
| 1697512 | Aug 2, 2019 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35375132 | Oct 3, 2019 | IN VIOLATION | — |
| 1776506 | May 18, 2019 | FAILURE TO COMPLY WITH THE COMMISSIONRS ORDER CONTAINED IN SUMMONS/ | Jan 30, 2020 | IN VIOLATION | — |
| 1425531 | Mar 23, 2019 | FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN SUMMONS/VIO#35375134 | Jan 30, 2020 | IN VIOLATION | — |
| 1203918 | Feb 11, 2019 | FAILURE TO SUBMIT A REQUIRED CYCLE 8A REPORT OF CRITICAL EXAMINATION D | Jul 25, 2019 | IN VIOLATION | — |
| 1422669 | Jan 25, 2019 | FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTED: PREMISES | Sep 5, 2019 | IN VIOLATION | — |
| 1162519 | Jan 3, 2018 | TEMPORARY CONSTRUCTION EQUIPMENT SIDEWAK SHED 146584455 EXPIRED | May 24, 2018 | IN VIOLATION | — |
| 1073229 | Jan 30, 2017 | FAILURE TO MAINTAIN EXTERIOR BLDG SOUTH ELEVATION EXPO #1 OBSERVED FLO | Apr 20, 2017 | IN VIOLATION | — |
| 1178347 | Oct 19, 2016 | FAILURE TO MAINTAIN EXTERIOR BLDG FRONT ELEV EXP#1-DECORATIVE PARAPET | Dec 8, 2016 | STIPULATION/IN-VIO | — |
| 1203893 | Mar 7, 2016 | FAILURE TO FILE AND ACCEPTABLE TECHNICAL REPORT IN COMPLIANCE W/CODE | Sep 8, 2016 | IN VIOLATION | — |
| 1151344 | Jun 2, 2015 | FAILURE TO MAINTAIN FACADES AND APPURTENANCES. NOTED: AT EAST EXPOSURE | Jul 23, 2015 | STIPULATION/IN-VIO | — |
| 1203779 | Sep 19, 2014 | FAILURE TO FILE AN ACCEPTABLE CYCLE 7 TECHNICAL REPORT IN COMPLIANCE W | Dec 4, 2014 | IN VIOLATION | — |
| 1764643 | Aug 12, 2012 | FAILURE TO FILE AN ACCEPTABLE SIXTH ROUND TECHNICAL REPORT IN COMPLIAN | Nov 15, 2012 | IN VIOLATION | — |
| 1203544 | Dec 15, 2011 | FAILURE TO FILE AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCE | Apr 12, 2012 | IN VIOLATION | — |
| 1203490 | Jan 25, 2011 | FAILURE TO FILE AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCE | Jun 2, 2011 | IN VIOLATION | — |
| 1203390 | Jul 6, 2010 | FAILURE TO FILE AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCE | Aug 26, 2010 | DEFAULT | — |
| 659920 | May 14, 2010 | FAILURE TO MAINTAIN BLDG WALL(S)OR APPURTENANCES.NOTED:@ SOUTH ELEVATI | Jul 8, 2010 | DEFAULT | — |
| 1203306 | Mar 29, 2010 | FAILURE TO FILE AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCE | Jul 1, 2010 | IN VIOLATION | — |
| 1202841 | Nov 21, 2008 | FAILURE TO SUBMIT AN ACCEPTABLE SIXTH ROUND TECHNICAL REPORT IN COMPLI | Jan 14, 2010 | IN VIOLATION | — |
| 944451 | May 4, 2007 | FAILURE TO MAINTAIN EXTERIOR BLDG WALL DEFECTS NOTED EAST WALL OF REAR | Oct 4, 2007 | IN VIOLATION | — |
| 745021 | May 14, 2003 | PLUMBING WORK W/O PERMIT LOCATION THROUGHOUT BLDG GAS BOILERS GAS LINE | Jul 3, 2003 | IN VIOLATION | — |
| 364513 | Jan 2, 2002 | OCCUPANCY CONTRARY TO THAT ALLOWED BY THE COFO. NOTED; 4TH FLOOR OF SA | Apr 5, 2002 | STIPULATION/IN-VIO | — |
| 727199 | May 25, 2001 | FAILURE TO MAINTAIN BUILDING.NOTED:BROKEN,CRACKED,DEFECTIVE STAIRS, LA | Jul 12, 2001 | WRITTEN OFF | — |
| 725111 | Dec 2, 1998 | FAILURE TO MAINTAIN BLDG. NOTED: FRONT STAIRWELL BROKEN, RUSTED & | Jan 21, 1999 | WRITTEN OFF | — |
| 414567 | Jun 25, 1998 | 74#-FAILURE TO FILE WITH THIS DEPT. FOR ELEVATOR DISMANTLE AND OR REMO | Aug 13, 1998 | WRITTEN OFF | — |
| 593614 | May 12, 1998 | FAILURE TO SUBMIT A FOURTH ROUND TECHNICAL REPORT: PERIODIC INSPECTION | Jul 2, 1998 | WRITTEN OFF | — |
| 858822 | Apr 6, 1998 | FAILURE TO MAINTAIN BUILDING EXTERIOR NOTED: AT FRONT FACADE OF BUILDI | May 28, 1998 | WRITTEN OFF | — |
| 588569 | Apr 25, 1994 | FAILURE TO SUBMIT A THIRD ROUND TECHNICAL REPORT. PERIODIC INSPECTION | Aug 25, 1994 | WRITTEN OFF | — |
| 650068 | Oct 20, 1988 | FAILURE TO MAINTAIN EXTERIOR BUILDING WALL DEFECT IS BRICKWORK CRACKED | Mar 30, 1989 | WRITTEN OFF | — |
| 943482 | Oct 20, 1988 | FAILURE TO MAINTAIN EXTERIOR BLDG. WALL DEFECT IS: BRICKWORK CRACKED A | Jan 12, 1989 | WRITTEN OFF | — |