94 Mott Street

ManhattanBIN 1002615
6 open Class C$10,000.00 recorded as due
Export CSV
OverviewHealth scoreTimelineFinesOwner
Open Class C
6
Immediately hazardous
Open Class B
33
Hazardous
Open Class A
1
Non-hazardous
Fines due
$10,000.00
Balance on OATH/ECB summonses
Permits on file
7
DOB permit records
Last activity
Jun 26, 2026
DOB record

Building health score

A composite of public indicators. Every input is a public record. See the full methodology.

D
Health score · Jul 29, 2026
Scored from all 160 public records for this building
Open Class C violations
Immediately hazardous, uncertified
This building 6
Open Class B violations
Hazardous
This building 33
Heat & hot water records
Violations and complaints, last 24 months
This building 0
Unpaid penalties
OATH/ECB summonses with balance due
This building $10,000
Bedbug filings with infestations
Annual LL69 filings on record
This building 0
Tenant litigation
Open HP actions in Housing Court
This building 0
Active vacate order
HPD or FDNY order to vacate, still in effect
This building No

Unified timeline

Every record from every agency, interleaved. 160 records on file.

Download this timeline (CSV) →
Jun 26, 2026
Jun 16, 2026
Apr 28, 2026
Apr 28, 2026
Apr 24, 2026
Apr 21, 2026
Apr 21, 2026
Apr 21, 2026
Mar 23, 2026
Nov 14, 2025
Nov 14, 2025
Nov 19, 2024
Sep 23, 2024
Sep 23, 2024
Jun 7, 2024
Dec 1, 2023
Nov 22, 2023
Jun 30, 2023
Jun 30, 2023
Jun 30, 2023
Jun 30, 2023
Jun 20, 2023
Jun 20, 2023
Jun 20, 2023
Jun 20, 2023
Apr 25, 2023
Apr 25, 2023
May 5, 2021
Aug 31, 2020
Aug 25, 2020

OATH / ECB summonses & fines

$10,000.00 is recorded as due across the 28 summonses below, out of $37,850.00 in penalties imposed. The city’s published records do not show whether a penalty was paid, reduced, or written off.

OATH and ECB summonses for 94 Mott Street
1216423Jun 16, 2026RESPONDENT FAILED TO COMPLY WITH 1RCNY 103-15(B), WHICH REQUIRES THAT Sep 3, 2026PENDING$2,500.00
1600086Jun 7, 2024FAILURE TO FILE REQUIRED ANNUAL BOILER INSPECTION REPORTS FOR LOW-PRESAug 22, 2024DEFAULT
1608643Aug 25, 2020FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING. NOTE: AT TIME OF INSPECTIONApr 22, 2021IN VIOLATION$2,500.00
1608630Aug 25, 2020AT TIME OF INSPECTION,OBSERVED ONGOING CONSTRUCTION ACTIVITIES CONTRARApr 22, 2021IN VIOLATION$5,000.00
1776686Feb 10, 2016FAILURE TO COMPLY W/THE COMM'S ORDER CONTAINED IN NOV #35153915N ISSUEMar 31, 2016IN VIOLATION
1759302Nov 16, 2015FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN NOV #3515Dec 31, 2015IN VIOLATION
1093797Jun 4, 2015OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERTIFICATE OF OCCUPANCY OR Aug 13, 2015IN VIOLATION
1489974Mar 19, 20152(B201). FOUND WEIL MCLAIN CGA-6 175,000 BTU BOILER AND AO SMITH HW420May 7, 2015STIPULATION/IN-VIO
1472061Feb 9, 2011FAILURE TO COMPLY W/ COMMS ORDER TO CORRECT CONDITION CITED IN NOV#348Mar 31, 2011IN VIOLATION
483736Feb 9, 2011OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERT OF OCCUPANCY OR BLDG DEMar 31, 2011IN VIOLATION
483739Feb 9, 2011BC1001.1 27-357 MISC VIOLATION FAILURE TO PROVIDE REQUIRED MEANS OF EGMar 31, 2011IN VIOLATION
483798Feb 9, 2011FAILURE TO COMPLY W/THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF Mar 31, 2011IN VIOLATION
402546Nov 30, 2010WORK W/O A PERMIT (100% OF WORK COMPLETED). NOTED: INSTALLATION OF DUNApr 1, 2011IN VIOLATION
480219Nov 30, 2010SEC. 27-366 FAILURE TO PROVIDE 2 MEANS OF EGRESS FROM EVERY FLOOR. NOTApr 1, 2011IN VIOLATION
480210Nov 30, 2010OCCUPANCY CONTRARY TO THAT ALLOWED BY THE C OF O. NOTED: C.O. #106241 Apr 1, 2011IN VIOLATION
796357Aug 4, 2009ALTERED/CHANGED BUILDING OCCUPIED W/O A VALID C OF O AS PER 28-118.31 Sep 24, 2009IN VIOLATION
749106Jul 8, 2009FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER. USE OF PROHIBITED DAug 27, 2009IN VIOLATION
785603Jul 8, 2009ALTERED/CHANGED BLDG OCCUPIED W/O A VALID C OF O AS PER 28-118.3.1-28-Aug 27, 2009IN VIOLATION
663105Aug 6, 2008ALTERED/CHANGED BLDG OCCUPIED W/O A VALID C/O AS PER 28-118.3.1 - 28-1Sep 25, 2008IN VIOLATION
531420Jun 7, 2006OCCUPANCY CONTRARY TO THAT ALLOWED BY C OF O #106241 ISSUED DEC 14,94-Jul 27, 2006STIPULATION/IN-VIO
655003May 31, 2006BQ9,50A,50B,51,50C/BQ9-NO WORK PERMIT FOR THE INSTALLATION OF 2 HOTWATDec 14, 2006IN VIOLATION
270445Apr 12, 199616Jul 18, 1996WRITTEN OFF
270414Apr 12, 199618B,49, NIPPLE IN BLOW DOWN LINE CORRODED BAD LEAKING TO REPLACE BY NEJul 18, 1996WRITTEN OFF
50171May 18, 199418B,48AJul 28, 1994DEFAULT
49025May 18, 199448BJul 28, 1994DEFAULT
96139Nov 9, 1993ALTERED BUILDING OCCUPIED WITHOUT A VALID COFO. ALT.#1748/86. LOCATIONJan 20, 1994STIPULATION/IN-VIO
113289Aug 8, 199132 2ND VALVE IN BLOW DOWN & WATER COLUMN DRAINS TO FIT (B) FLUE PIPE NOct 31, 1991DEFAULT